Kaiming Work Safety Licence Record: Why Is Piping Prefabrication Scheduled before Shutdown?

The official website records the issuance information of the Work Safety License. The Qinghai soda ash industry agreement schedules pipeline prefabrication before shutdown, and jointing, equipment replacement, and inspection testing after shutdown; accordingly, the steam shutdown plan is reviewed to distinguish the conditions for prefabrication completion, on-site safety handover, and subsequent processes.

According to the qualifications page on the official website, the Work Safety Licence held by Wuhan Kaiming High-Tech Co., Ltd. is numbered (Hubei) JZ An Xu Zheng Zi [2023]002220. It was issued by the Hubei Provincial Department of Housing and Urban-Rural Development on 2026-02-28, with a stated expiry date of 2029-02-28. When planning maintenance during a steam shutdown, verify the company's licence and distinguish between preparations that can be completed in advance and operations that must wait until the plant (owner) has shut down, isolated and safely handed over the equipment.

How the Qinghai Soda Ash Agreement Allocates Work before and after Shutdown

The mechanical services section of the official website lists an agreement for the soda ash industry in Qinghai: pipeline prefabrication is scheduled prior to shutdown, followed by pipeline tie-ins, sequential replacement of flash vessels, pipeline inspection, hydrostatic testing, and purging after shutdown. The listed items reflect the agreed schedule; actual downtime duration is not specified.

This arrangement provides a specific comparative method for the maintenance plan: first, identify pipe segments that can be pre-fabricated in advance according to the scheme, and then schedule the tie-ins with the original system and subsequent inspections within the shutdown window. If all preparations commence only after the shutdown, the pre-fabrication sequence outlined in this protocol is not adopted; whether the schedule can be advanced remains subject to the scope of the local pipe segments and site conditions.

Completing prefabrication does not mean that the conditions for piping tie-ins have been met

The official website’s “Boiler Steam Shutdown Maintenance Work Package” schedules the shutdown, isolation, and handover prior to repair and replacement. The plant, the contractor, and the inspection team each assume specific responsibilities. Following repair and replacement, inspection and testing, as well as the handover for operational restoration, are required.

When reviewing the schedule on this basis, if the prefabricated pipe sections are ready but the plant (owner) has not completed shutdown, isolation and safe handover, the conditions for site work are still pending. Tie-in work cannot be scheduled to start unconditionally at a set time. Even after site handover, the sequence must allow for piping inspection, hydrostatic testing and purging. Installing the new pipe alone does not mark the end of the entire shutdown window.

Wuhan Kaiming High-Tech Co., Ltd. undertakes the removal and replacement of large equipment and the replacement of piping, coordinating mechanical, electrical and welding trades. If flash vessels must also be replaced one by one during the same shutdown window, schedule equipment replacement and the subsequent piping operations separately in accordance with the agreement. Identify which operation still lacks the required conditions rather than covering everything with a single, general "maintenance completion date".

The aforementioned sequence is used for protocol review and scheduling, and does not provide operational parameters for isolation, pressure testing, or return to service; specific implementation shall be carried out in accordance with the approved plan for this unit.

Source: "Wuhan Kaiming High-Tech Co., Ltd. Qualification Certificate List: System Certification, Testing, and Production License"; "Shutdown for Component Replacement and Equipment Installation: From Lifting and Positioning to Trial Run Handover"; "Boiler Steam Shutdown Maintenance Work Package".

Source information

Kaiming high-tech certificates and awards: holders, dates and honours · Contract project directory: 602 equipment and service records

Tell us about your equipment.

Send equipment details and maintenance needs. Our team will contact you.

Contact our team ↗
Call usLeave a message
S0X-261124-09