Project records for steam pipelines and boiler components
The table records Kaiming’s previous work in steam-pipeline modification, pipe removal and replacement, and boiler-component installation and repair. It lists the agreed work month, region, equipment and work description for each entry.
| Agreed month of pipeline work | Industry | Region | Equipment or component | Work description |
|---|---|---|---|---|
| 2025-05 | Soda production | Qinghai | Steam pipelines; dense-soda desuperheating and pressure-reduction equipment | Steam-pipeline optimisation and modification; installation of desuperheating and pressure-reduction equipment and associated facilities;Contractor: Hubei Kaiming High-Tech Co., Ltd. |
| 2025-10 | Combined heat and power | Not specified | Steam-recovery water tank, 316L stainless-steel steam pipelines and distributor | Pipe removal, replacement and installation; fabrication and welding of steam distributor and pipe blind flanges |
| Not specified | Power generation | Hubei | Gears, coal mill, boiler, large gear | Maintenance and repair |
| Not specified | Chemical processing | Hubei | Steam sootblowing pipes for a high-pressure boiler superheater | Installation |
The Qinghai soda-project agreement includes removal and reinstallation of flash vessels, associated pipes and valves; new steam pipelines and desuperheating and pressure-reduction equipment; and installation of pipe racks, insulation and metering facilities. Shutdown tie-in work also includes pipeline inspection, hydrostatic testing and blowing.
Wuhan Kaiming High-Tech Co., Ltd. handles installation notification, commissioned supervisory inspection and assistance with use registration. The contractor submits material inspection reports, construction records and concealed-work acceptance records. The combined heat and power project also requires quantity-confirmation documents and completion-acceptance application records.
The Hubei chemical-plant sootblowing-pipe project initially planned to retain some pipes around the boiler. Site inspection found thinning, and material requirements had changed. Additional pipes and elbows were therefore added at the original contract unit rates.