Record the kiln before and after alignment against the same datum
A Kaiming rotary-kiln mechanical-overhaul contract sets out the sequence. Before work, measure tyre-to-pad clearances, shell deformation and dimensions for spare-part manufacture, and record the original structural data. Then replace pads, repair spalled areas, carry out on-line turning and grinding, and adjust the kiln line and support rollers.
The contract requires Kaiming to supply support-roller adjustment values and procedures from the measurements and lead implementation with client assistance. A diagnostic report and cold-state adjustment guidance are also included. Completion records cover the installed kiln line, support-roller slope, clear spacing, tyre-pad creep, total runout and axial wobble, together with post-adjustment measurements and a formal written monitoring report. Accept operations in sequence and confirm concealed work before proceeding. Repair, turning and grinding also require before-and-after photographs and inspection data, plus assistance with the client's trial run.
Each measurement-point record lists operating conditions, the drawing or manual reference value, pre-adjustment readings, post-adjustment readings and the confirming person. Use the same datum before and after adjustment. These records form the verification baseline after the kiln next starts. Agree equipment-specific acceptance limits in the technical agreement using that kiln's drawings.