Shell replacement: from support to weld inspection
The shell and support-roller replacement plan proceeds through site and spare-part checks, shell support, cutting layout, removal and lifting of the old shell, positioning and alignment of the new shell, welding and support-roller replacement. Inspect cuts and bevels, joint mismatch, axis, radial runout and weld quality. Dimensional limits follow equipment drawings and the technical documents agreed by both parties.
A Hubei cement-enterprise contract specifies replacement of a 4.8-metre shell section on a nominal 2500T/D rotary kiln, concentricity inspection and adjustment, and manufacture of kiln-jacking supports. The 4.8 metres identifies the contracted replacement-section length.
Acceptance under that contract covers joint flatness, coaxiality and weld quality. Welds must pass ultrasonic testing, followed by joint physical acceptance and a signed report. Separate time clauses cover mobilisation, site repair and execution. Each has its own starting point; actual kiln downtime requires operating records.