Prepare before shutdown and work to the assembly sequence
A Qinghai soda-project agreement schedules piping prefabrication before shutdown, then tie-ins, individual flash-vessel replacement, piping inspection, hydrostatic testing and blowing during shutdown. A Hubei soda-calciner contract separately includes a tyre-replacement bar chart. Prepare delivery checks, tools and lifting routes beforehand where possible, reserving the shutdown window for dismantling, removal, placement, alignment and reassembly checks.
Pressure-bearing industrial piping installation is itemised separately within GC2. For each section, provide its purpose, material, medium, design and operating pressures and temperatures, interfaces and shutdown isolation conditions, then connect piping work to mechanical reassembly milestones.