Assess each machine’s condition and impact on restart before fixing the scope. The Hunan mixer method statement proceeds through static inspection and adjustment, static low-spot repair, dynamic testing, machining while rotating and system adjustment. Send removable rolls for workshop repair in advance, checking ultrasonic and penetrant testing and the reassembly date.
For a shutdown covering several metallurgical machines, use condition data to assess deterioration and restart impact, then define each repair scope. Prioritise equipment where continued running would worsen faults or restrict output, and work back from the longest sequence.
Method statements prepared by Wuhan Kaiming High-Tech Co., Ltd. for a Hunan steel project distinguish on-site inspection and alignment from off-site repair of removable parts.
Assess granulator wear and vibration first
The March 2023 method statement records a φ3800×17500 mm drum granulator at a Hunan steel enterprise after 20 years of operation. Support rollers, thrust rollers, girth gear, pinion and tyres showed wear and pitting; the tyres were distorted and gear and support-roller vibration was increasing.
The July 2022 mixer method statement specifies tyre-to-pad clearance, shell slope, support-roller slope and centreline, girth-gear axial and radial runout, and gear tip clearance, followed by comparison with the drawings.
The mixer sequence has five steps: static inspection and adjustment; repair of tyre low spots while stopped; dynamic inspection after rotation starts; in-situ turning and grinding of support rollers and tyres while rotating; and system adjustment using the measured data.
Dynamic inspection and dynamic machining both require rotation. Allow time for each when scheduling back from restart.
Send removable rolls for repair in advance
Removable parts such as rolls can be sent off site before shutdown and refitted during the outage, separating their repair time from the shutdown window.
The workshop off-line repair contract for 10 cantilever rolls at a Hunan steel enterprise was signed on 2021-07-19; the performance register records completion on 2021-12-11, with ultrasonic and penetrant testing required.
List site and off-site work separately, identifying repair, replacement, standards and the acceptance person for each machine. Allow margin for hidden work discovered after dismantling, and have spare parts in stock before shutdown.
Before restart, collect measurement, repair, machining and adjustment records under one equipment identifier. Check dimensions, testing and adjustment data against the agreed standards, then confirm individual-machine operation and running under load. Define the standards in the work list before work starts.
For cross-province attendance from Wuhan, Hubei, agree the equipment location and shutdown window with Kaiming.
Shutdown-maintenance enquiries: 13995571345, 13349867738.
Questions & answers
How should several machines be prioritised for maintenance?
Rank them by condition data and restart impact, prioritising faults worsened by continued running or equipment that restricts output, then schedule back from the longest sequence.
Which mixer and drum-granulator method statements are available?
Kaiming has Hunan steel project method statements for inspection, alignment and support-roller and tyre repair, including tyre restoration and in-situ turning and grinding.
What if roll repair takes longer than the shutdown window?
Send removable rolls off site in advance and refit them during shutdown. The Hunan contract for 10 cantilever rolls ran about five months from signing to completion.
What needs checking before restart?
Check dimensions, flaw detection and adjustment data against the standards agreed beforehand, then confirm individual-machine and loaded operation separately.