This Henan cement-enterprise tyre plan sets a size difference of ≤0.5 mm, surface finish ≤Ra3.2 and passing flaw testing as delivery requirements. Wuhan Kaiming High-Tech Co., Ltd. also includes system inspection and alignment in response to repeated cracking. Use those items to review the actual part's requirements.
A Henan building-materials plant comparing pre-restart repair options can begin by listing each option's acceptance criteria in one table.
One reference is the second-station rotary-kiln tyre plan prepared by Wuhan Kaiming High-Tech Co., Ltd. for a Henan cement enterprise in July 2023.
Kaiming repairs worn surfaces on building-materials and cement equipment. Its work covers repair plans, layered deposition or weld overlay, on-line turning and grinding, flaw testing and post-repair dimensional remeasurement.
The Henan records mainly concern kiln tyres, support rollers, thrust rollers and mill slide shoes for cement enterprises. One tyre plan also includes kiln-system inspection and alignment.
The project table separates contracting legal entities. The references cited here involve Wuhan Kaiming High-Tech Co., Ltd. and Hubei Kaiming High-Tech Co., Ltd.; retain the entity stated on each source row.
Compare the repaired surface with the adjacent sound surface
The plan requires a size difference of ≤0.5 mm between the repaired surface and adjacent sound surface, checked with a steel rule and feeler gauge. Surface finish at the repaired area must be ≤Ra3.2, with delivery after passing flaw testing.
During grinding, compare the surface with the dedicated arc gauge and templates made on site to control its arc profile and flatness.
The specified bond-quality measures use KM1# bonding material to reduce hot and cold cracks, with local staged preheating and temperature control before deposition.
Why repeated cracking also calls for kiln measurement and alignment
This kiln had undergone shell-bending correction in earlier years, followed by first-station support-roller heating and repeated second-station tyre cracks. The plan therefore includes system inspection and alignment, followed by on-line turning and grinding of the out-of-round tyre to restore flatness and surface finish.
The inspection report uses a three-dimensional model to present the centreline, shell ovality, deflection, eccentricity, runout, and support-roller and tyre running angles.
Other published Henan entries include two July 2021 cement-enterprise records for grinding mill front- and rear-end slide shoes; middle-station support-roller weld repair in June 2015; and kiln, support-roller, tyre and thrust-roller repair and overhaul with weld overlay in March 2025.
These published rows all belong to the cement industry within the wider building-materials sector and can be checked under that industry.
Ask about four items when comparing proposals: pre-repair wear measurement, evidence of bond quality, post-repair remeasurement items, and the signatory for those measurements.
The company is based in Wuhan, Hubei. Agree attendance in Henan against the current kiln-shutdown window.
Business enquiries: 13995571345, 13349867738.
Questions & answers
Which reference values cover repaired-surface size difference and finish?
This Henan tyre plan from Wuhan Kaiming High-Tech Co., Ltd. specifies ≤0.5 mm and surface finish ≤Ra3.2. Set the actual part's criteria from its own drawing.
What else does the plan include for repeated tyre cracking?
The plan identifies kiln running as a possible cause of the cracking and therefore includes system inspection and alignment.
How should records be filed and signed before restart?
File the repair process, final dimensions, flaw-testing results and inspection and alignment reports under the same equipment number, with separate signatures from the executor and confirmer.